The Tariff Hit Your Bid. Whether It Hits Your Margin Is Still Up to You.

Margin Protection

Material costs and tariffs are hitting fixed-price work hard. The contractors protecting margin decided what they’d do before the quote came in.

The short answer

Contractors protect margin from tariffs and material inflation by running the business like a thermostat, not a thermometer. A thermometer measures cost increases after they land. A thermostat has 3 parts set in advance: lines in the sand (margin and cost floors), signals (specific triggers that show a line was crossed) and predefined responses (escalation clauses, repricing and client calls that happen on a deadline).

Key takeaways

  • From September 2025 to September 2026, copper mill shapes rose 30%, steel mill products 28% and aluminum mill shapes 25% (BLS data via AGC).
  • 55% of contractors had at least one non-data-center project canceled, postponed or scaled back in the prior 6 months. Rising costs were the top reason (AGC-NCCER, 2026).
  • A thermometer reports the temperature. A thermostat holds it. Most construction businesses run like thermometers.
  • The thermostat needs all 3 parts: lines in the sand, signals and predefined responses.
  • Building yours takes a working document and about 3 hours.

You submitted that bid 8 months ago.

Steel was running where it had been for a while. You priced it accordingly, built in a reasonable contingency and won the job. Fixed price. Good client. Workable timeline.

This week your supplier sent a revised quote. From September 2025 to September 2026, producer prices for copper mill shapes rose 30%. Steel mill products rose 28%. Aluminum mill shapes rose 25%. Steel, aluminum and copper carry tariffs of up to 50%. Softwood lumber carries 10%.

The job you won is the job you’re losing money on.

You’re not alone. In the 2026 AGC-NCCER Workforce Survey, 55% of contractors reported at least one non-data-center project canceled, postponed or scaled back in the prior 6 months. Rising costs were the most common reason. Earlier in the year, ABC found construction input prices rose at a 12.6% annualized rate in January and February alone.

Every owner in your market is reading the same numbers. Most are doing the same thing with them: measuring the damage, calculating the exposure and waiting to see what happens next.

That’s understandable. It’s also the wrong response. Not because you’re uninformed, but because measuring what’s happening and managing through it are 2 different things.

What’s the difference between a thermometer business and a thermostat business?

A thermometer business measures cost changes after they land. A thermostat business decides in advance what it will hold and what it will do when conditions drift.

Here’s a framework I use with clients when markets turn volatile.

A thermometer tells you what the temperature is. Accurate, useful, completely passive. When the environment shifts, it shifts with it. That’s all it does.

A thermostat holds a temperature. It’s set to a target, and when conditions drift from that target, it activates. It doesn’t report the environment. It responds to it, until things return to where you decided they need to be.

Most construction businesses run like thermometers. They watch the material market, track last quarter’s margins and adjust pricing after the fact. In a stable environment, that’s fine.

It stops working when input prices climb at a 12.6% annualized pace.

The thermometer vs. thermostat framework. A framework from Jane Gentry of JaneGentry & Co. for running a business through volatility. A thermometer business measures conditions and reacts after the fact. A thermostat business sets 3 things in advance: lines in the sand (floors, not goals), signals (observable triggers that show a line was crossed) and predefined responses (actions decided before the pressure arrives). All 3 are required.

What are the 3 parts of a construction thermostat?

Lines in the sand, signals and predefined responses. A thermostat isn’t a mindset. It’s a system, and it only works when all 3 parts are in place.

1. Lines in the sand

These are the numbers your business needs to stay profitable. Not goals. Floors. The point at which something has to change. Right now, for a construction business, those lines might look like:

  • Gross margin by contract type: fixed-price work must stay above 18%.
  • Material cost ceiling by input: the steel price at which the contingency on active bids is gone.
  • Backlog coverage: below 14 weeks of signed work, business development activates immediately.
  • Bid variance: if a supplier quote comes in more than 12% above the estimate assumption, that bid doesn’t go out at the original number.

These aren’t targets you’re hoping to hit. They’re the lines you’ve decided to defend.

2. Signals

A signal tells you a line has been crossed. The critical part is that you define the signal before the market moves, so you’re not deciding in the moment whether things are serious enough to act. You already decided that. The signal fires, and a response happens.

Signals for a construction business right now:

  • A supplier quote that exceeds your material assumption by more than your threshold
  • A contract’s gross margin dropping below your floor during execution
  • Backlog coverage falling below your minimum
  • A tariff change that touches a material category in your active bids or submitted estimates

3. Predefined responses

This is where most businesses stop short, and it’s the whole point of the system. When a signal fires, you shouldn’t be deciding what to do. You should be executing what you already decided when you were thinking clearly, before the pressure was on.

Here’s what that looks like right now:

  • Steel exceeds your threshold: Every new bid includes an escalation clause. Existing fixed-price contracts with steel exposure get a renegotiation call within 5 business days. Not when it feels right. Within 5 business days.
  • A contract’s gross margin drops below your floor: The owner reviews it within 1 week. A client conversation happens. It does not get quietly absorbed while you hope the next job makes up for it.
  • Backlog drops below your minimum: Stop waiting for inbound work. Start calling your relationship list. Today.
  • A supplier quote comes in more than 12% above your estimate: That bid doesn’t go out at the original price. It gets repriced, rebid with a different material spec, or carries a written contingency the client has to acknowledge before you proceed.

The predefined response is what separates a thermostat from good intentions. The lines and the signals are preparation. The predefined response is the actual protection.

What does a thermostat look like when tariffs hit?

It looks like calls going out before clients start to wonder.

I worked with a mechanical contractor who had drawn exactly these lines. When the tariff announcements hit in early 2026, he didn’t call a meeting to figure out how bad it was. He pulled up the response he’d written 6 months earlier and started making calls.

Within 10 days, he’d initiated renegotiation conversations on 3 fixed-price contracts, added escalation clauses to 2 of them and adjusted his bidding assumptions going forward. His clients heard from him before they had time to wonder what was happening.

That’s not luck. That’s a system.

The contractor in the next county, same market and same material exposure, spent those same 10 days in reactive conversations he wasn’t prepared for. One of those clients is now in dispute. The relationship may not survive it.

Same tariff environment. Different outcomes. The difference was the work that got done before the signal fired.

Measuring what’s happening and managing through it are 2 different things.

What are most contractors doing instead?

Scrambling.

The revised quote hits the estimator. The estimator goes to the project manager. The project manager goes to ownership. Everyone calculates how bad it is. Someone calls the client. The client pushes back. An uncomfortable conversation happens under pressure, with no framework for how it should go, at a moment when the relationship is already strained.

Meanwhile, the bids from the past 6 to 12 months sit unreviewed. Nobody has gone through contract by contract to figure out which ones are underwater and by how much. That review feels like it can wait, until it can’t.

And the second-order effects catch them off guard. Flooring contractors and product suppliers serving commercial construction feel project delays in their installation volume 3 to 6 months later. The thinning pipeline doesn’t show up in your backlog today. It shows up in your schedule 4 months from now, when there’s far less room to respond.

How do you build a thermostat in 3 hours?

You don’t need new software. You need a working document and 3 hours.

Step 1: Draw your lines in the sand. Write down the floor for each variable your margins depend on. At minimum:

  • Gross margin floor by contract type
  • Material cost ceiling for your top 3 input categories
  • Backlog coverage minimum in weeks
  • Maximum variance between your estimate assumption and an incoming supplier quote before a bid gets repriced

Step 2: Define your signals. For each line, write the specific, observable event that tells you it’s been crossed. “Steel prices are high” is not a signal. “My supplier’s steel quote exceeds $X per ton” is a signal. Be precise enough that there’s no debate about whether it fired.

Step 3: Write the response before you need it. For each signal, define exactly what happens:

  • Who gets notified, and within what timeframe?
  • Which client conversations get initiated, and who makes the call?
  • What changes on bids going out this week?
  • What gets escalated to ownership versus handled at the project level?

Post it where your team can see it. Review it quarterly. Update the lines when your cost structure changes.

What should suppliers to commercial construction do?

Run the same diagnostic on your own customers.

If you supply into commercial construction (flooring, specialty products, anything tied to project timelines), look hard at your manufacturing clients right now. In the Institute for Supply Management’s December 2025 forecast, 32% of manufacturing leaders said they planned to pass all of their tariff-related cost increases to customers. Another 42% planned to split it, passing some on and absorbing the rest.

That repricing is hitting their customers now. The volume assumptions they built their plans around may already be wrong, and yours, downstream of them, may be too.

What’s your line in the sand on their order volume? What’s the signal? What’s the response when it fires?

Is your thermostat set?

Tariffs may ease. Some of the postponed projects will restart. Conditions will shift in directions nobody is calling accurately right now.

The thermometer business will adjust when they do. The problem isn’t whether it adjusts. It’s what the adjustment costs when it happens after the fact, under pressure, without a framework for the conversation.

The thermostat business already answered the harder question: what does this company need to stay profitable, and what happens, specifically and immediately, when the environment moves away from that?

Most owners can answer the first question. Fewer have a working answer to the second.

If you’re recognizing the gap (lines you’ve never drawn, signals you’ve never defined, responses that live only in your head), that’s a 3-hour problem, not a year-end problem.

Questions owners ask

How can contractors protect margin from tariffs on steel, aluminum and copper?

Set margin floors and material cost ceilings before prices move, define the specific supplier quote or price level that triggers action, and decide the response in advance. That response usually includes escalation clauses on new bids, renegotiation calls on exposed fixed-price contracts within 5 business days, and repricing any bid where a supplier quote exceeds the estimate by a set percentage.

What is the thermometer vs. thermostat framework?

It is a framework from Jane Gentry of JaneGentry & Co. A thermometer business measures conditions and adjusts after the fact. A thermostat business sets targets and activates predefined responses when conditions drift. The thermostat has 3 required parts: lines in the sand, signals and predefined responses.

How much have construction material prices risen in 2026?

BLS producer price data compiled by AGC show copper mill shapes up 30%, steel mill products up 28% and aluminum mill shapes up 25% from September 2025 to September 2026. AGC also reported construction input costs up 8.9% from August 2025 to August 2026. Steel, aluminum and copper carry tariffs of up to 50%.

What should be in an escalation clause decision?

Decide in advance which materials and price thresholds trigger an escalation clause on new bids, which existing fixed-price contracts get a renegotiation call, who makes that call, and the deadline. Writing it down before prices move keeps the conversation from happening under pressure with no framework.

Why do tariffs affect flooring contractors and suppliers later?

Project delays upstream reach installation trades and product suppliers roughly 3 to 6 months later. The thinning pipeline doesn’t show up in today’s backlog. It shows up in the schedule months later, when there’s less room to respond.

Sources

  1. AGC, “Average annual percent change, construction materials” (BLS PPI data, Jan. 2020 to Sep. 2026). https://www.agc.org/sites/default/files/users/user21902/Average%20annual%20percent%20change%20construction%20materials%202026_Sep.pdf
  2. AGC, “Construction Input Costs Climb 8.9% Between August 2025 and August 2026,” Sept. 10, 2026. https://www.agc.org/news/2026/09/10/construction-input-costs-climb-89-between-august-2025-and-august-2026-association-survey-finds-war
  3. AGC and NCCER, 2026 Workforce Survey national release, Sept. 3, 2026. https://www.agc.org/sites/default/files/users/user21902/2026%20Workforce%20Survey%20National%20Release%20(5).pdf
  4. Construction Dive, “Construction input prices rise at ‘staggering’ rate” (ABC analysis, Jan. and Feb. 2026). https://www.constructiondive.com/news/staggering-construction-prices-february-2026/815257/
  5. Manufacturing Dive, “Manufacturers plan price hikes over reshoring to combat tariff effects” (ISM Supply Chain Planning Forecast, Dec. 2025). https://www.manufacturingdive.com/news/manufacturers-plan-price-hikes-over-reshoring-to-combat-tariff-effects-ism/808157/

About Jane Gentry

Jane Gentry is a strategic operating model advisor and former CEO who ran two private-equity-backed companies. An operator by background, she works with mid-market CEOs at companies between $20M and $800M in revenue. She redesigns org structure, decision rights, and workflows when revenue grows faster than the business was built to run. For more, visit www.janegentry.com. Connect on LinkedIn.

Free 15-minute scorecard

What has your company outgrown?

Seven areas, one test question each. See where the way your company runs has fallen behind its size.

Get the Operating Debt Scorecard

Want a second set of eyes on your lines in the sand?

Jane works directly with mid-market CEOs on who owns what, how decisions get made and where work stalls. Start with a 30-minute conversation.

Book a 30-minute consultation

Originally published in Commercial Construction & Renovation. Adapted for janegentry.com.

Jane Gentry is a strategic operating model advisor and former CEO of two PE-backed companies who helps mid-market CEOs redesign their companies when revenue grows faster than the business was built to run.